Archive for December 2009
Project Database YEAR 2009
Project Name | Project Owner | Original Contracted Amount | Final Contract Amount | Project Manager | Date Completed |
---|---|---|---|---|---|
Morning Star Farms / Field Clean-up | CG Construction | $9,830.00 | $9,830.00 | Monte Molina | 12/04/09 |
Dingville Duck Club | Ducks Unlimited | $149,884.60 | $217,791.00 | Monte Molina | 11/20/09 |
Equipment Rental | CG Construction | $10,781.00 | $10,781.00 | Monte Molina | 11/12/09 |
Putah Creek Perc Dam Removal | KO Construction | $62,294.11 | $62,294.11 | Monte Molina | 11/03/09 |
Upper Butte Basin / Field 205 | Ducks Unlimited | $35,257.00 | $35,257.00 | Monte Molina | 10/07/09 |
Owner/Operator job | CG Construction | $17,550.00 | $17,550.00 | Monte Molina | 09/29/09 |
San Pablo Bay | Ducks Unlimited | $254,521.40 | $272,660.40 | Monte Molina | 09/23/09 |
Oakley Project | CG Construction | $18,070.00 | $18,070.00 | Monte Molina | 09/22/09 |
Gray Lodge – Field 93 Swale Re-grade | Ducks Unlimited | $6,624.00 | $6,624.00 | Monte Molina | 07/09/09 |
Gray Lodge | Ducks Unlimited | $18,343.44 | $18,343.44 | Monte Molina | 07/09/09 |
Wildlands Rental | CG Construction | $36,334.09 | $36,334.09 | Monte Molina | 07/05/09 |
Wister Wildlife Area – Dozer work | California Waterfowl Assoc. | $3080.00 | $3080.00 | Monte Molina | 06/17/09 |
Salton Sea Conservatory | California Waterfowl Assoc. | $56,650.00 | $56,650.00 | Monte Molina | 06/17/09 |
Million Dollar Duck Club | California Waterfowl Assoc. | $34,460.00 | $34,460.00 | Monte Molina | 06/16/09 |
Wister Wildlife Area | Ducks Unlimited | $140,890.00 | $140,890.00 | Monte Molina | 06/03/09 |
Pond Construction & Channel Improvements | Ducks Unlimited | $47,840.00 | $47,840.00 | Monte Molina | 06/03/09 |
Dozer Work T14, U14, W11C & Y16 | California Waterfowl Assoc. | $14,000.00 | $14,000.00 | Monte Molina | 06/01/09 |
W11C Unit & Ditch work | California Waterfowl Assoc. | $68,950.00 | $68,950.00 | Monte Molina | 06/01/09 |
Fields Y16 A&B | California Waterfowl Assoc. | $149,440.00 | $149,440.00 | Monte Molina | 05/27/09 |
Duck Stamp WCS Install | California Waterfowl Assoc. | $6,710.00 | $6,710.00 | Monte Molina | 05/04/09 |
Ridgeway #1 | California Waterfowl Assoc. | $64,000.00 | $64,000.00 | Monte Molina | 04/15/09 |
Ridgeway #2 | California Waterfowl Assoc. | $27,450.00 | $27,450.00 | Monte Molina | 04/15/09 |
Y16 A&B Dozer Work | California Waterfowl Assoc. | $5,600.00 | $5,600.00 | Monte Molina | 04/15/09 |
Y16 A&B Tree/Shrub Removal | California Waterfowl Assoc. | $11,480.00 | $11,480.00 | Monte Molina | 04/02/09 |
Palo Verde | California Waterfowl Assoc. | $13,450.00 | $13,450.00 | Monte Molina | 03/20/09 |
Wister Duck Stamp Leveling | California Waterfowl Assoc. | $33,000.00 | $33,000.00 | Monte Molina | 03/20/09 |